Timeline

We hope to submit a planning application to Westminster City Council shortly. The timeline below outlines where we are in the planning process:

  1. Initial Consultation & Pre-Application Discussions with Westminster City Council - 2019 Complete
  2. Online consultation - July 2020 In Progress
  3. Application Submission - August 2020 Upcoming
  4. Planning Approval - January 2021 Upcoming
  5. Demolition Start - November 2021 Upcoming
  6. Construction Start - March 2022 Upcoming
  7. Frame & External Envelope Completed - April 2023 Upcoming
  8. Completion - February 2024 Upcoming